PROJECTS

DESIGN, CONSTRUCTION AND EQUIPMENT OF A WATER TREATMENT PLANT (WTP)

Saurimo (Angola)

The goal of this project is the design, construction and equipping of a new water treatment plan (WTP) to supply the city of Saurimo with drinking water, to meet the consumption demands of a population of ~600k, the WTP needs to have 60,000 m3 capacity. The project includes the following scope: water intake; raw water transmission network; new WTP; new water distribution centres and water transmission network.

Implementation: 2023 - 2025
Contract value: €157.000.000

CONTRACTING AUTHORITY

Ministry of Health
Government of Angola

INVOLVED PARTIES

Sinohydro
Main contractor -
Technological Partner

Quantum
Subcontractor

Standard bank
Financing agent